20 Vestas Turbines to Power 124 MW Haute-Chaudière Wind Project in Québec

July 15, 2026 by Zara Wright
Advertisement
20 Vestas Turbines to Power 124 MW Haute-Chaudière Wind Project in Québec

QUÉBEC – June 18, 2025 – Global wind turbine manufacturer Vestas has secured a 124 MW order from EDF Power Solutions North America (EDFps) to supply 20 EnVentus V162-6.2 MW turbines for the Haute-Chaudière wind project in Québec. The order also includes a 10-year Active Output Management 5000 (AOM 5000) service agreement to ensure high performance and reliability of the turbines.

Strategic Partnership with Long-Term Vision

The Haute-Chaudière Wind Project represents the latest in a decades-long collaboration between Vestas and EDFps, spanning over 2.9 GW of wind energy across North America. The project is one of three awarded by Hydro-Québec following a competitive tender and supports the province’s goal of adding 10 GW of wind capacity by 2035.

“This project shows how effective partnerships and technology can drive Québec’s clean energy future,” said Laura Beane, President of Vestas North America.

Local Jobs and Canadian Supply Chain

The project highlights local economic development, with Québec-based Marmen contracted to manufacture the wind turbine towers. This partnership is expected to support 130 direct jobs in Trois-Rivières.

“We’re proud to work with Canadian partners like Marmen to reinforce the importance of a domestic supply chain,” said Tristan Grimbert, CEO of EDFps North America.

[internal_link url=”]

Project Timeline and Impact

Turbine deliveries are scheduled for the second quarter of 2026, with commissioning planned for the fourth quarter. Once operational, Haute-Chaudière will supply clean electricity to tens of thousands of Québec homes while driving regional industrial development and contributing to the province’s energy transition goals.

FACTSHEET: Haute-Chaudière Wind Project

  • Location: Granit RCM (Frontenac, Audet, Lac-Mégantic), Québec
  • Turbines: 20 Vestas EnVentus V162-6.2 MW
  • Total Capacity: 124 MW
  • Developer: EDF Power Solutions North America
  • Turbine Supplier: Vestas North America
  • Tower Supplier: Marmen (Trois-Rivières)
  • Job Creation: 130 direct jobs
  • Service Agreement: 10-year AOM 5000
  • Delivery Start: Q2 2026
  • Commissioning: Q4 2026
  • Grid Integration: Hydro-Québec distribution network
Categories News

Recent Posts

  • Washington releases funding for Mobile River Bridge Project Alabama
  • Waterpark finally ready to open its doors 16 years after the announcement in UK.
  • Wellstar Health Receives Approval for $1 Billion Acworth Hospital, Georgia
  • West Virginia Breaks Ground on $1.2B, 600MW Wolf Summit Power Plant
  • Western Gateway Pipeline Advances After Securing Key Shipper Commitments

Unlock more content

Take action to continue accessing the content on this site

View a short ad
Site-wide access for 24 hours
© 2026 Construction Cycle | Privacy Policy | Terms of Service | Cookie Policy | Contact Us | About Us